Introduction: Operation
breakdown of
a basic T-shirt means to find out different parts and elements
of a basic t-shirt for sewing one after another. Industrial engineers do this
job and planning the production process or working flowchart to manufacture a
basic t-shirt. Basic t-shirt produces from knit fabric. It's
GSM range 130-180. A basic t-shirt is more comfortable and
flexible than a Polo t-shirt.
Common
parts of a basic T-shirt: If we breakdown a basic T-shirt, we
will find some common parts;
- Neck rib
- Front part
- Back
Part
-
Left sleeve
-
Right sleeve
-
Left sleeve hem
- Right sleeve hem
- Bottom Hem
Operation
Breakdown of a basic t-shirt with total cycle time: Operation Breakdown of a basic T-shirt is done by the following table;
SL. No. | Name of Operation | Each Operation Cycle Time | Calculated Production at 100% Efficiency |
---|---|---|---|
1 | Care Label Attach With Back Part | 0.20 | 300 |
2 | Front & Back Part Match | 0.18 | 333 |
3 | Shoulder Joining | 0.33 | 181 |
4 | Neck Rib Measure & Cut | 0.25 | 240 |
5 | Neck Rib Tack With Body | 0.26 | 230 |
6 | Neck Rib Joining | 0.30 | 200 |
7 | Neck Top Stitch | 0.25 | 240 |
8 | Main Label Attach | 0.33 | 181 |
9 | Sleeve Hem | 0.30 | 200 |
10 | Sleeve & Body Match | 0.22 | 272 |
11 | Sleeve Joining | 0.42 | 142 |
12 | Arm Hole Top Stitch | 0.30 | 200 |
13 | Side Seam | 0.57 | 105 |
14 | Sleeve Close & Open Tack | 0.37 | 162 |
15 | Body Hem | 0.46 | 130 |
16 | Final Thread Cut | 0.34 | 176 |
Total Cycle Time | 5.08 |
Table - 1: Operation Breakdown of a Basic T-shirt
From the above table, we get operation breakdown and total cycle time. We also estimate each operation production target which helps us line balancing and preparing machine layout.
You may like: Operation Bulletin of a Basic T-shirt with Machine Layout Plan.
SMV calculation of a Basic T-shirt:
Problem: From the above table, we find total cycle time is 5.08,
suppose the performance rating of all operator is 80% for a basic T-shirt. Now,
Find out the SMV for that Basic T-shirt.
Solution:
We know,
SMV = Basic time + Allowance
= ( Cycle time ×
Rating) + (Bundle allowances + machine and personal allowances)
= (5.08 × 0.80) + (Bundle
allowances + machine and personal allowances)
= 4.06 + ( 5.08 × 10%)+
(5.08 × 20%)
= 4.01 + 0.508 + 1.016
= 5.58
So, we find out SMV for that Basic T-shirt is 5.58 minute.
Production target calculation of a basic T-shirt:
Problem: We find SMV for that basic t-shirt is 5.58.
Suppose, No. of worker of that line is 22, the efficiency of that line
85%. Find out the production target per day of that basic t-shirt in one sewing line.
Solution:
Here,
SMV = 5.58 Minute.
No. of worker = 22.
Line efficiency = 85% = 0.85
We know, Total working hour in a day = 8 hr.
Now,
Production Target = {(Total manpower per
line × Total working min per day )/ S.M.V.} × Efficiency
= { (22 × 8 ×
60) / 5.58 } × 0.85
= 1608.60 ~ 1609
= 1609 pieces.
So, Daily production target = 1609 pieces in one sewing line
and Hourly production target = 1609 / 8
= 201.13~ 201 pieces /
hr.
= 201 Pieces/hr in one sewing line.
= 201 Pieces/hr in one sewing line.
So, From this post, we learn about Operation breakdown of a Basic
T-shirt, Total Cycle Time, SMV calculation, and Production target in daily and
hourly.
Thank you for your patient reading. Is the article helpful? Please, share this article with others.